PRO-FILES: Field & Stream Durafloor HP Installation

 

Location: Cranberry Township, PA
Contractor: Concrete Resources
Total Sq Ft: 30,000 done in 3 Phases.
Existing substrate: approximately 25 years old.

Tuesday - Surface Prep

  • Grind existing floor with 30 grit metal segment diamonds.
  • Vacuumed, broomed, and washed existing floor.
  • Placed 3/8 Terrazzo strips, anchored with Locktite caulk.

Wednesday - Mix and Place Epoprime bonding agent

  • Mixed and squeegeed Epoprime epoxy primer bonding agent.
  • Broadcast silica sand to refusal.
  • Left sanded epoxy to cure overnight.

Thursday - Mix and Place Durafloor HP

  • Broomed excess sand from surface.
  • Mixed and placed Durafloor HP using Strong pump with 1.5 diameter, 250 long hose and 2 men using 3/8 gauge rakes.
  • Total placement time for 12,000 sq ft (Phase 2): approximately 2.5 hours